fien
Contact us tel. +358 9 439 0060 | info-acre (at) aalto.fi

Search

fien

Worksite news

02
August

Noise and vibration nuisances around the Väre site

The expansion of Väre/excavation work in Maarintie 13 will start at the beginning of week 33 (15 August 2016). The expansion section will be connected to block 4 of the original new building, inside the current worksite fences.

Work stages generating noise include pile driving and boring, as well as […]

18
March

Changes to pedestrian and bicycle routes near library

Figure 1: The new fence line and pedestrian and bicycle routes in the proximity of Lehmuskuja and Otaniementie.

SRV Rakennus Oy will move the worksite area fence line according to figure 1 on 21 March 2016. The move is caused by the transfer of infrastructure in the area. This will […]

07
January

Noise and trembling near Väre site

The construction of Väre in Otaniemi was launched on 28 December 2015. The work may cause noise and trembling in the area.
Noisy work phases include excavation support with steel joints, pile driving (hammer/drill) and the drilling of geothermal heat wells.

Noisy work will be launched on Monday, 11 January 2016, and […]

11
December

Construction work on the Väre building begins – Otaniementie to be closed

Several major construction projects are underway on the Otaniemi campus. Construction on Väre will begin next week in the area between Otakaari 1 and Tietotie 1, with the area being fenced off as a construction.

Due to construction work on Väre, Otaniementie will be closed to traffic between Vuorimiehentie and […]

25
November

Otaniemi campus changing at speed – earthwork to begin

Earthwork for the New Building (Väre) will begin in the middle of the campus, next to the metro station in the area between Otakaari 1 and Tietotie 1, on 1 December. The Väre building is due for completion in spring 2018, and it will be used by the Aalto […]

04
November

Major changes to private car and public transport in Otaniemi

The construction of the New Building (Väre) of Aalto University and the modification of the campus area centre in Otaniemi will be fully launched in December 2015. Preparations have already been made throughout the summer and autumn.

The renovation and area improvement will take about two-and-a-half years, and the work […]

16
October

Ongoing road construction works in Otaniemi

There are currently several construction sites in Otaniemi due to the launch of construction work on the new campus building Väre.

In the attached map, the sites that will be active between October and December are indicated in orange.

(Click the map)

The construction of roundabouts continues in Otaniemi

The construction of the Otaniementie – Servin Maijan tie roundabout will begin through the preparation of temporary traffic arrangements on Monday, 19 October 2015. The roundabout will be built in three phases: The first phase will take approximately three weeks. New signs will be installed along pedestrian routes, indicating all routes […]

05
October

The construction of roundabouts begins in Otaniemi – get ready for changes in traffic arrangements

The construction of the Vuorimiehentie–Otaniementie roundabout will begin through the preparation of temporary traffic arrangements on Monday, 5 October 2015. The roundabout will be built in three phases: The first phase will take approximately four weeks, during which time the current locations of bus stops will not be changed. […]

26
August

Changes in traffic arrangements in Otaniemi

Otaniemi prepares for the construction work of the new Väre building. Public transportation will move to a temporary route later in the autumn, and the parking on Puumiehenkuja will change to parallel. Jokioisten Maanrakennus Oy is responsible for the implementation of the work.

During September and October, changes will also […]