New building Väre and Maarintie 13

Inventive architecture & academic pulse

Earthwork for the New building (Väre) and Maarintie 13 in the central campus area between Otakaari 1 and Tietotie 1 has begun.

The Väre building will be used by the Aalto University School of Arts and Design. The total floor area of the building will be approximately 33 000 gross square metres. In addition to Aalto University’s functions, Väre will contain the new Metro Centre and its commercial services. In addition to the university’s own operation, the centre will house shops, business facilities and services. The rental of the facilities has progressed on schedule, and more than 80% of the business facilities have already been rented out. The start date for the metro has not been confirmed, yet.

Väre is based on the winning entry by Verstas Architects in the architectural design competition in 2012–2013. The fresh and clear architectural character of the core campus building will enable flexible, interdisciplinary encounters and a variety of spatial arrangements.

At Maarintie 13 in the northern part of the large construction site, work is starting on the new building for the School of Business. At the moment, excavation work is carried out at the site and the construction of the frame of the building will start in spring 2017. The building should be completed in summer 2019.

Have a look at the construction site through webcam!

Watch a video >

Changes in traffic arrangements

Light traffic

Public transport

Private traffic

Timeline and next steps

1

October–December 2015

Earthwork and traffic arrangements in Otaniemi began in summer 2015. The last preparatory road work for the Väre construction site, such as the new roundabouts, were completed during the winter.

2

December 18th, 2015

Otaniementie closed, traffic detoured. The arrangement affects pedestrian and cycle traffic as well as public and private transport in central Otaniemi.

3

March 2016 – January 2017

Frame construction.

4

April 2016 – November 2017

Facade component installation and brickwork.

5

May 2016 – April 2018

Interior construction and technical building service installation.

6

August 2016

Maarintie 13 groundwork begins.

7

Spring–summer 2018

Furniture and device installation.

8

Fall 2018

Property in use.

Worksite news

27.04.2017
Changes to routes near Väre and Maarintie 13
Read more

02.08.2016
Noise and vibration nuisances around the Väre site
Read more

18.03.2016
Changes to pedestrian and bicycle routes near library
Read more

Join the mailing list

Your email address

Worksite weekly

26.04.2017
Weekly worksite bulletin – week 16
Read more

07.04.2017
Weekly worksite bulletin – week 14
Read more

28.03.2017
Weekly worksite bulletin – week 12
Read more